Home › Forums › General › Standards and codes › ASME IX-PQR
- This topic has 17 replies, 3 voices, and was last updated 7 years, 2 months ago by
Ballbearing.
-
AuthorPosts
-
February 5, 2018 at 1:28 am #1383
Flash
SpectatorHi Kav
the difference between A333Gr 6 and LF2 with regards to impacts results is significant isnt it
It is interesting to note that LF to ASME 16.5 only require 18J yet AS3992 requires 30J depending on material
I wonder if piping designers have ever picked up this miss matchout of interest what sort of impact numbers did you get and what size sample
RFebruary 5, 2018 at 2:47 am #1380Shane Kavanagh
SpectatorHi Thanks for the info, the material grade for the pipe was grade 6.
In the end i proceeded with the procedure using 50nb XS A333 Grade 6 one side and A350 LF2 the other side. Did 3 coupons.
This covers me for A1 and A2 material according to AS3992 -1998 and Group 1 and 2 in ASME IX
Construction Codes are as you stated B31.3 and AS4041.
For the mechanicals i had 2 x tensile, 2 macro, 2 x hardness, 2 x root bend, 2 x face bend and 1 x charpy v Notch@ -65.5C
Only had a slight tear on 1 of the bend test, 0.89mm but it still complied.
Hardness survey on the Macro was also done.
Overall the mechanicals and RT came back as complied. Now i need to get my client to approve the PQR and WPS.Currently writing the PQR followed by the WPS for AS3992, i will keep in mind the impact testing restrictions.
Thanks for your help, if you have any further comments i would appreciate them.
Regards
KavKav
February 5, 2018 at 3:52 am #1384Shane Kavanagh
SpectatorI’m sure they don’t along with many other things.
Test info
Test temp was -65.5, Size was 2.5×10, location was WMCLReadings were 1(18J), 2(20J), 3(24J) average 20.7J
Assessment result was a comply for AS/NZS 3992 and ASME IX, although i picked up on the report for ASME IX that they used the 2007 edition. I have asked them to recheck against the 2010 edition and resubmit.
My client advised this morning that the PQR and WPS have been approved without changes and are being submitted to there client for approval.
Those late nights at central TAFE and long drives from sunny Rockingham to get there are paying off 🙂
Regards
KavKav
February 5, 2018 at 4:10 am #1385Flash
Spectatorwhy didn’t you do haz impacts in pipe and flange
in my opinion the mech report should Ref B31.3 as this is where the impacts requirements for asme ix come fromR
FlashFebruary 5, 2018 at 4:22 am #1386Shane Kavanagh
SpectatorYes i did do HAZ also.
I will look into the b31.3 option. I’ll give them a call and talk to them about it. Thanks for the info.
Regards
KavKav
February 5, 2018 at 4:23 am #1387Flash
Spectatorso don’t keep me in suspense
what did the flange come up at
R
GFFebruary 5, 2018 at 4:34 am #1388Shane Kavanagh
SpectatorFebruary 5, 2018 at 4:37 am #1389Flash
SpectatorThats the hardness report
– neat trick adding the image file –February 5, 2018 at 4:53 am #1390Shane Kavanagh
SpectatorSorry i miss understood you, The only impacts i had done was the weld metal center line.
I did however do a 4th coupon at the same time as the 3 used for the procedure and collected all my coupons back and mechanical tested parts so further testing could be carried out in the future.
Regards
KavKav
February 5, 2018 at 5:01 am #1391Flash
SpectatorSmart move getting coupons for later testing
some specs call for wmcl, fl, fl+2, fl+5 and it is painful to run them all again for thatI would have done the haz impacts done as well, one set in the pipe and one set in the flange
it really depends on your design temp and consumable classification, but without going into detail and looking at your test temp you might want to check into it a little furtherR
FlashFebruary 5, 2018 at 5:04 am #1392Flash
SpectatorCheck this out Kav
this is not the only one I have done and most have similar results
R
F
impact example.pdfAttachments:
You must be logged in to view attached files.February 5, 2018 at 5:14 am #1393Shane Kavanagh
SpectatorWow, big difference between the pipe and the flange material….!
I will defiantly look into getting some more testing done.
Regards
KavKav
February 5, 2018 at 5:20 am #1394Flash
Spectatorto be perfectly honest instead of testing the welding procedure you end up doing a random batch test on the flange material, if it does fail in my opinion it is because the quality of the forging is suspect
because the flange values will vary depending on when and where they are made
I have seen some good some not so good
Let us know how ya goR
FlashFebruary 5, 2018 at 6:35 am #1376Ballbearing
SpectatorKav,
As Flash has stated forget about diameter when you are qualifying welding procedures. Only comes into play for Welder Qualifications.
What grade of SA 333 are you using ? (there are 8 grades)
What fabrication code are you working to ? (I’m presuming B31.3 for ASME and AS 4041 for Australian)
Are impacts required ? If so the goal posts change significantly.
A bit more info and we can probably assist more,
Regards,
BBFebruary 5, 2018 at 6:43 am #1467Ballbearing
SpectatorKav,
Sorry for late reply but have a quiet day and trawling through old postings.
Flash is correct – to comply with B31.3 you should have performed 3 x WM, 3 x HAZ (A333) and 3 x HAZ (LF2)
Have a look at Table 323.3.1 in B31.3,
Regards,
BB -
AuthorPosts
- You must be logged in to reply to this topic.